Original CDMlogic guide · updated · Great Britain CDM / England or Wales Building Regulations where stated
Start by checking the project’s transitional position. The date alone does not determine which requirements apply to existing work.
What changed?
Wales introduced Building Regulations dutyholder and competence provisions under Part 2B of the Building Regulations 2010. Clients, designers and contractors have defined responsibilities. These are separate from CDM 2015 health and safety duties.
The same organisation can undertake both Principal Designer roles, but must be competent for each; where it does, the client must confirm the dual appointment in writing. Keep the responsibilities distinct.
Who needs to do what?
Clients need suitable project arrangements and competent appointments. Designers address compliance through their design work; the Building Regulations Principal Designer coordinates design compliance. Contractors and the Principal Contractor have corresponding construction responsibilities.
Competence includes skills, knowledge, experience and behaviours, alongside organisational capability where applicable. A familiar job title does not establish competence for a particular project.
Domestic clients: check the Welsh position
Do not copy England’s domestic-client assumptions. Welsh guidance permits domestic clients to appoint themselves to principal roles, but strongly recommends suitably experienced professionals unless they are sure of their competence. Without appointments, the designer and contractor controlling the respective phases take those principal roles.
Read the Welsh Government dutyholder and competence guidance for the full duties and appointment rules.
Does an existing project move to the new rules?
The transitional guidance distinguishes the general amendments from higher-risk building procedures. For the general Building Regulations amendments, work started, plans deposited or a building notice given before 1 July 2026 can preserve the earlier requirements. Initial notices have separate provisions. Rejected plans or notices, or notices ceasing to be effective, can change the position.
For higher-risk work, the guidance addresses full plans deposited or an initial notice accepted or deemed accepted before that date. It also identifies circumstances in which transitional protection ends. Do not use a simple “project started before July” test for every case.
Record the route, relevant dates and supporting documents, then check the official transitional arrangements with the project’s building control team.
Higher-risk buildings have additional procedures
The Welsh reforms include approval before higher-risk building work starts, completion approval, change control, mandatory reporting and a golden thread of information. These additional procedures should not be applied indiscriminately to every project. Confirm classification using the Welsh definition and exclusions rather than importing England’s criteria.
Use the Welsh Government overview and its linked regulations to identify the applicable route.
A practical starting checklist for your practice
This is a suggested review routine, not a statutory form or exhaustive compliance checklist.
- Record that the project is in Wales and identify the building control route.
- Gather submission, notice and commencement evidence before recording a transitional conclusion.
- Check higher-risk classification and document the reasoning.
- Identify the client type and record each role, appointment and scope separately.
- Ask what evidence supports competence for the specific work, and identify gaps.
- Agree who reviews design changes, communicates decisions and maintains the record.
- Set a review point when scope, appointments or the approval position changes.
For a structured evidence discussion, use the Principal Designer competence guide and downloadable checklist. It starts with the CDM appointment review and explains why Building Regulations competence needs separate consideration.
Where CDMlogic fits today
CDMlogic’s core pilot workflow supports CDM 2015 records. This guide does not introduce a Welsh Building Regulations approval, competence assessment or golden thread system. England-labelled draft templates should not be treated as ready-made Welsh appointment documents.
Use the guide to prepare questions for your project team. Read our regulatory scope and guide to the two Principal Designer roles before deciding how to organise the records.
Continue your project review
- Health & Safety File contents and handover guide
- Worked design risk register example
- CDM software for architects
- CDM Principal Designer software
- Pre-construction information checklist
- Design risk assessment and register guide
- CDM and Building Regulations Principal Designer roles
- CDM workflow for architectural practices
General workflow information, not a project-specific determination. Check current official guidance and obtain appropriate professional advice for your project.