DESIGN DECISIONS

Design risk assessment and register: a practical CDM guide

A design risk review process for architects: compare options, record decisions, communicate residual information and use a free editable register.

Original CDMlogic guide · updated · Great Britain CDM / England or Wales Building Regulations where stated

What is a design risk assessment?

A design risk assessment is the review behind a design decision: what could cause harm, who could be affected and how the design can address it. A design risk register keeps a usable record of that review, the remaining information and the actions others need to take.

For architects, the useful output is a clearer design and timely information. A completed spreadsheet or a low risk score does not, by itself, demonstrate that the design is suitable.

Start with the design decision

HSE explains that designers must consider available pre-construction information and, so far as reasonably practicable, eliminate foreseeable risks through design. Where elimination is not possible, reduce or control them and provide the information other dutyholders need.

See HSE’s designer duties. The steps below are CDMlogic’s suggested way to organise the review, not a prescribed statutory form.

Free editable design risk register

Download an Excel workbook with a blank register, a fictional worked example and instructions. Track design decisions, information gaps, actions, evidence and communication.

Download the editable register (Excel) ↓

No sign-up · version 1.0, 17 October 2026 · manual review statuses, no automatic risk or compliance verdict. Save a project copy and read the Instructions sheet before use.

A practical design risk review process

  1. Define the decision. Name the element, drawing revision and stage. “Rear extension roof access” is more useful than a project-wide heading of “working at height”.
  2. Check what is known. Link the relevant survey, existing record or design brief. If a decision depends on missing information, record the question and who will resolve it. See the PCI checklist.
  3. Compare design options. Explain what could remove the problem and what alternatives were considered. Record the reason for the chosen arrangement and any assumptions that still need checking.
  4. Review the remaining issue. Say what another person needs to understand about this design. Keep an unanswered question visible rather than treating an assumption as confirmed evidence.
  5. Communicate and follow through. Identify the recipient, drawing or information reference and outstanding action. Record when it was actually shared; uploading a file alone does not show that the relevant person received it.
  6. Review when the design changes. Link the superseded entry to the new revision. A changed specification, survey finding or maintenance arrangement can change the earlier decision.

What should a design risk register contain?

Use enough detail for a colleague to understand the decision without reconstructing it from an email trail. Our editable workbook provides a starting point; adapt the fields to the project.

Context and reference
Project, entry ID, element, drawing or specification revision and review stage.
Issue and people affected
The foreseeable harm being considered, relevant activity and the people whose work or access is affected.
Options and decision
Options reviewed, the chosen design, reasons, constraints and assumptions needing confirmation.
Remaining information
Significant residual information, linked evidence and any unresolved design or information question.
Action and communication
Named owner, next review point, recipient, issue reference and the record of actual communication.

HSE’s CDM guidance L153, paragraphs 84 and 89–90 explains proportionate information and sharing it at the right time. Focus attention on significant design issues; avoid burying them in repeated generic warnings.

Fictional example: access to an extension rooflight

A small practice is reviewing a single-storey domestic extension. The proposed rooflight may need cleaning and replacement. The entry starts as an open design question, not an instruction for somebody to use a ladder.

  • Information gap: confirm the product’s maintenance requirements and the intended access arrangement.
  • Options to review: a product cleanable from inside, a different location or a different roof arrangement. Compare the implications with the relevant designers and product information.
  • Record: the selected option and reason, drawing revision, supporting information and any question that remains unresolved.
  • Next action: the architect coordinates the review with the relevant contributors before the affected design information is issued. Record what was communicated and to whom.
  • Review trigger: the rooflight product, position or maintenance requirements change.

This is an example of a record structure, not a roof-access design or a safe system of work. Follow the filled-in refurbishment register example to see a different decision and its evidence trail.

How does this relate to contractor RAMS?

RAMS means risk assessments and method statements.

The design review explains the design choice and the information needed to plan the work. It does not provide the contractor’s site-specific method or construction arrangements. HSE’s contractor guidance explains their responsibilities for planning and managing work. Share the relevant design information early enough for that planning.

When is a shared project register useful?

A spreadsheet may suit a small team and a limited number of entries. A shared workspace becomes useful when colleagues need to follow owners, evidence and outstanding questions across projects. CDMlogic connects those records with PCI and project reports; the team still assesses the design and carries out its duties.

See the fictional project tour or discuss the free pilot for your practice.

Continue your project review

General workflow information, not a project-specific determination. Check current official guidance and obtain appropriate professional advice for your project.